Decision 67767

Case Number Claimant Judge Language Decision date
Decision 67767   Goulard G.  French 2007-02-15
Decision Appealed Appellant Corresponding Case
Dismissed  No Commission  -


Issue: Sub-Issue 1: Sub-Issue 2: Sub-Issue 3:
earnings  commissions 

Summary:

The employer, a travel agency, had confirmed that the commission had been earned only when the trip had been confirmed. The delay in paying was simply due to the need to confirm the actual cost of the trip. The Board could therefore find that the commission had to be allocated to the week in which the services were rendered that gave rise to the commission.