Decision 19034
Case Number | Claimant | Judge | Language | Decision date |
---|---|---|---|---|
Decision 19034 | Martin | English | 1991-01-17 |
Decision | Appealed | Appellant | Corresponding Case |
---|---|---|---|
Allowed | No | N/A | - |
Issue: | Sub-Issue 1: | Sub-Issue 2: | Sub-Issue 3: |
---|---|---|---|
labour dispute | participation | picket lines |
Summary:
Whether or not they would honour the picket line was taken out of their hands when they discovered that the general contractor had shut the project down and he would not permit them on the work site. They did not reach the position of having to decide whether they would refuse.